RFP, RFQ, RFI: what is the difference and how should you respond?
RFI, RFQ and RFP are three different procurement requests. Learn what each one asks for, when buyers use it, and how to answer it without wasting effort.
If you sell to governments, public agencies or large companies, you will receive three kinds of documents again and again: the RFI, the RFQ and the RFP. They look alike, they are often sent by the same procurement team, and they are regularly confused, even by buyers. Yet each one asks a different question, and answering the wrong way is one of the most common reasons suppliers lose deals they could have won.
This guide explains what each request means, where it sits in the buying process, and how to adapt your response. If you are new to tenders, start with what public procurement is and how the tender process works.
The short version
| RFI | RFQ | RFP | |
|---|---|---|---|
| Stands for | Request for Information | Request for Quotation | Request for Proposal |
| The buyer is asking | "Who can do this, and how?" | "How much for exactly this?" | "How would you solve our problem, and at what price?" |
| Stage | Early exploration | Purchase decision | Selection among solutions |
| Requirements | Still vague | Fully specified | Defined by outcomes |
| Main selection criterion | None: no contract is awarded | Price and compliance | Best value: quality, method, price |
| Effort to answer | Low to medium | Low | High |
RFI: the buyer is still learning
A Request for Information is a market survey. The buyer knows it has a need, but not yet which solutions exist, what they cost, or which suppliers are credible. An RFI usually asks about your company, your experience, your technology and sometimes indicative prices.
No contract is awarded after an RFI. That is why many suppliers ignore them, and it is a mistake. The RFI is often the only moment when you can influence how the future RFP will be written: which standards it references, which features it requires, how it weighs price against quality. Suppliers who answer RFIs thoughtfully tend to find tenders later that fit them well.
How to answer an RFI:
- Be informative, not promotional. The reader is building an understanding of the market.
- Explain the options and trade-offs, including the ones you do not sell. It builds trust.
- Give realistic price ranges rather than a firm quote.
- Ask for a meeting or a demonstration if the rules allow it.
RFQ: the buyer knows exactly what it wants
A Request for Quotation is used when the requirement is fully specified: a quantity of standard equipment, a defined service with a clear scope, spare parts, licences. Every compliant offer is considered equivalent, so the decision comes down to price, sometimes combined with delivery time or warranty terms.
How to answer an RFQ:
- Follow the price template exactly. Offers that change the format are often rejected.
- Quote precisely what is asked. Alternatives are usually not accepted unless the RFQ explicitly allows them.
- Check the commercial conditions: validity period of the offer, delivery terms (Incoterms), payment terms, currency.
- Do not spend days on a technical memo nobody will read. Speed and accuracy matter more.
RFP: the buyer wants the best solution, not only the lowest price
A Request for Proposal is used when the need is complex and several approaches are possible: building a network, implementing software, running a service for several years, delivering a construction project. The buyer describes its objectives and constraints, then compares how each supplier proposes to meet them.
RFP evaluations are usually based on weighted criteria, for example 60% technical quality and 40% price. The technical score typically covers your understanding of the need, your methodology, your team, your references and your plan for managing risks.
How to answer an RFP:
- Start with the evaluation grid. Structure your answer so that each criterion is easy to find and score (see how tender evaluation works).
- Answer the buyer's problem, not your brochure. Reuse the buyer's own words and show you understood its context.
- Prove what you claim with similar references, named team members, figures and measurable commitments.
- Check eligibility first: turnover thresholds, certifications, bid bonds and mandatory documents. A brilliant proposal is worthless if it is disqualified on paperwork.
- Use the clarification period to ask questions. Answers are generally shared with all bidders, and good questions show you are serious.
Other acronyms you will meet
- RFT (Request for Tender): the common term in the UK, Australia and many public administrations. In practice it is very close to an RFP.
- ITB (Invitation to Bid) / IFB (Invitation for Bids): widely used by development banks such as the World Bank. It is often closer to an RFQ, with detailed specifications and a lowest-evaluated-price rule.
- EOI (Expression of Interest): a first step used to build a shortlist, frequent for consulting assignments. Only shortlisted firms then receive the full RFP.
- PQ (Prequalification): suppliers prove their capacity (financial, technical, legal) before being allowed to bid.
Why the distinction matters for your win rate
Many teams answer every request the same way: a long proposal for a simple RFQ, or a bare price list for a complex RFP. Both approaches lose. The first wastes time on a decision that will be made on price. The second fails to earn the technical points that decide an RFP.
Before you start writing, ask yourself three questions:
- What decision is the buyer making? Learning about the market (RFI), buying a known item (RFQ), or choosing an approach (RFP)?
- How will my answer be scored? Read the evaluation criteria before anything else.
- Is this opportunity worth the effort? An RFP can take days or weeks of work. Bid only where your chances are real: a bid/no-bid framework helps.
Knowing which document you are holding is the first step to answering it well. The second is finding the right opportunities early enough to prepare properly, and that is exactly where most suppliers fall behind.